Our Tsuboniwa(Courtyard) House: also known as The Tatami House
Monday, December 14, 2009
Day 243: Window and Doors!
We survived the rain just fine, the roof work is finishing up.
Windows, Sliding Glass Doors, Kitchen Table, Desk and Front Door arrived today!
The incredible front door!
Friday, December 4, 2009
Day 235: Rain is Coming!
2 storms are excepted to hit next week! They assured me that the roof will be done and the skylight holes will be covered in plastic.
Master bathtub is in!
Today's job site condiment is Dijon Mustard with White Wine.
Saturday, November 28, 2009
Day 229: Roof Almost Done
Short week because of the holiday. Roof is almost done and electrical and plumbing continues.
Saturday, November 21, 2009
Day 222: Work Continues....
Electrical work continues, some of the changes have not been done yet or done incorrectly... time to send off an email.
Some of the radiant floor heating system components have been installed.
Older Posts
Subscribe to:
Posts (Atom)
Archive
▼
2009
(54)
▼
December
(2)
Day 243: Window and Doors!
Day 235: Rain is Coming!
►
November
(4)
Day 229: Roof Almost Done
Day 222: Work Continues....
Day 215: Roof, Electrical & Tiles
Day 214: Roof Work
►
October
(6)
Day 201: Nutmeg?
Day 194: Blue Sky
Day 191: Meeting & Skylights
Day 190: Framing Complete - Roof Work Started
Day 180: Framing
Day 173: Framing
►
September
(6)
Day 169: Window Fabrication
Day 166: Panels Almost Done - Interior Framing
Day 159: Panels Almost Done
Day 152: More Panels
Day 145: More Panels
Day 141: More Panels
►
August
(6)
Day 137: Back Panels Up
Day 133: More Panels
Day 132: Panels Going Up
Day 130: First Group of Panels
Day 123: What's Going On?
Day 112: Concrete Test #2 and #3
►
July
(6)
Day 108: Framing Complete & Concrete Test
Day 105: Framing Continues II
Day 98: Framing Continues
Day 92: Framing Start
Day 88: Slab #1 Poured and Wall Preparations
Day 82: Floor Slab Preparation
►
June
(6)
Day 70: Steel Complete
Day 69: Steel
Day 68: Concrete Part 2
Day 62: Concrete!
Day 60: Footings
Day 53: Rebar
►
May
(8)
Day 45: More Formwork
Day 44: Foundation Work Continues
Day 41: Foundation Trenches
Dat 37: Foundation Work
Day 36: 3 Feet
Day 32: Grading Inspections
Day 28: Site Work Continues
Day 21: Progress?
►
April
(3)
Day 12: Excavating and Jichinsai
Day 6: String Lines for Foundation
Day 2: The House is Gone!
►
March
(4)
Yes we have Asbestos!
Asbestos????
Your days are numbered!
►
February
(1)
►
January
(2)
►
2008
(19)
►
December
(2)
►
November
(1)
►
October
(2)
►
September
(2)
►
August
(1)
►
July
(2)
►
June
(1)
►
May
(8)
Labels
Demolition
(3)
Doors
(1)
Electrical
(1)
Flooring
(2)
Foundation
(8)
Framing
(9)
Grading
(6)
other
(1)
Plumbing
(3)
Pre-Construction
(23)
Roof
(5)
Skylights
(1)
Structural
(3)
Tiles
(1)
Wall Panels
(13)
Windows
(2)
Links
P3 Flickr Set - Construction Photos
P3 Designwork - Portfolio
P3 Life - Blog
design*21
About Me
P3
View my complete profile